West Cambridge Data Centre
A purpose-built data centre of the University of Cambridge in the south-west corner of the West Cambridge site, beside the Coton footbridge and Ada Lovelace Road. Completed in 2014 at a cost of about 19.4 million pounds, shared between the University and Cambridge Assessment, it holds separate data halls for the University's central computing, its High Performance Computing Service and Cambridge Assessment, with a fourth hall kept empty for growth.
Timeline
5 December 2012: Other
The University's governing body approves the first-stage plan for a new data centre on the West Cambridge site. The aim is to replace ageing computer rooms with one efficient building, and the Planning and Resources Committee has already backed the full case a week earlier. The promised prize is a 40 per cent cut in carbon emissions and large savings in energy and maintenance over twenty years.
July 2013 to December 2014: Construction
Construction begins on the 19.4 million pound building, most of it funded from the University's own Capital Fund. The plan is to finish the shell and then move services across from older machine rooms by the end of 2014, with space for the new Chemical Engineering and Biotechnology Building's equipment inside the central computing hall.
2014: Founding
The data centre is completed and enters service, giving the University and Cambridge Assessment a shared home for their research computing, storage and examination systems. A fourth data hall stays empty on purpose, held back for future growth.