Urban Forest of Palma

The Urban Forest of Palma began as a stalled corner of a much bigger public park scheme, sat for decades as disused greyhound and cycling tracks, and only slowly turned into the green space it was meant to be. Planned in 2015 on the site of the former Canodromo Balear greyhound track and the Tirador velodrome in the Es Forti neighbourhood of Palma, it replaced an earlier, more conventional park design with one that kept traces of the old sports structures and gave over far more ground to trees. Its first phase opened to the public in July 2022 after repeated delays, while the second phase, covering the old velodrome, was not presented until 2025 and is not expected to be finished before 2027 or 2028. It has also been known, in its earlier incarnation, as part of the wider Sa Falca Verda park project.

Timeline

2002: Founding

The Palma City Council approves a large public park scheme called Sa Falca Verda, designed by architect Manuel Ribas Piera. It envisages absorbing the land of two already closed sports facilities, the Tirador cycling track, shut in 1973, and the Canodromo Balear greyhound track, shut in 1999, replacing their old structures entirely with new parkland.

2007: Construction

Work on the first piece of the wider scheme, the Parc de la Riera, opens to the public, while the section that will become the Urban Forest remains stuck. The Canodromo land cannot be expropriated until 2008, and the Tirador cycling track not until 2015, leaving the sports ruins standing for years after the original plan was approved.

28 December 2015: Renovation

The city council scraps the old Ribas Piera design for this corner of the site and presents a new, separate project called Bosc Urba, the Urban Forest, designed by architect Isabel Bennasar. Rather than clearing the old sports structures, her plan keeps them as a base for the new landscaping and greatly increases the amount of ground given to trees and vegetation.

27 July 2018: Construction

Building work finally begins on the first phase, covering the old Canodromo Balear greyhound track, after an earlier 2017 restart of the project also failed to keep to schedule. The contractors expect the job to take twelve months, but the deadline slips repeatedly over the following years.

29 July 2022: Construction

The first phase of the Urban Forest opens to the public, four years after building work began and two decades after the land was first earmarked for parkland. Some 280 trees, including holm oaks, maples, lime trees, olives, elms, pines, poplars, oaks and cypresses, now stand where the greyhound track once ran, alongside new drainage and irrigation systems using regenerated water.

22 May 2025: Renovation

The second phase, covering the old Tirador velodrome, is officially presented, designed by Isabel Bennasar together with Corina Dindareanu. It is expected to be carried out between 2027 and 2028, finally completing a park first proposed more than two decades earlier.