Tyne Bridge
The Tyne Bridge is a single-span steel arch carrying the road between Newcastle and Gateshead, and when it was built it was the largest single-span arch bridge in Britain. Its arch was built outwards from both banks at once, a method tried here before Dorman Long used it on Sydney Harbour Bridge. Designed by Mott, Hay and Anderson with towers by Robert Burns Dick, it was begun in 1925 to give work to Tyneside and opened by King George V in 1928, after three men had died building it. Originally called the New Tyne Bridge, it has since served as the city's emblem, a stage for celebrations and home to a colony of kittiwakes, and it is now midway through a long restoration aimed at its centenary.
Timeline
August 1925: Construction
Work starts on the New Tyne Bridge, built by Dorman Long of Middlesbrough to a Mott, Hay and Anderson design. The Tyne Improvement Commissioners forbid river piers and any lifting of material from barges, so the steel arch has to grow outwards from each bank on cables, cradles and cranes. It is thought to be the first use of this method in Britain, and a test bed for the Sydney Harbour Bridge that the same firm is building.
February 1926: Disaster
Frank McCoy of Gateshead is killed while the foundations are being sunk, when a skip of excavated material falls from a crane. He is the first of three men to die on the job. The inquest records accidental death.
18 February 1928: Disaster
Nathaniel Collins, a 33-year-old scaffolder from South Shields, falls from the top of the arch into the river and is killed. The steelworkers climb without safety equipment, and his death comes just days before the two halves of the arch are joined. The inquest records accidental death.
25 February 1928: Construction
The bridge is completed, with the arch closed across the river and the deck carried on it. It has taken about two and a half years and some 7,000 tonnes of steel, and nearly four years before Sydney Harbour Bridge will be finished. The total cost is £1,200,000, partly met by a government grant to ease shipbuilding unemployment on Tyneside.
June 1928: Disaster
Norman Muller, a joiner's labourer from Sunderland, falls from the north abutment tower while removing scaffolding, after the bridge is already finished. He is the third man to die on the bridge. The inquest records accidental death.
10 October 1928: Commemoration
King George V opens the bridge, and he and Queen Mary are the first to cross, in their Ascot landau. Local schoolchildren are given the day off to watch and are handed a commemorative brochure, and Movietone News films the King's speech. The towers were meant to hold warehouses, but their upper floors are never fitted out.
2000: Renovation
The bridge is repainted in the green of 1928, in the same colours as the original paint. A major refurbishment follows in 2001, the year the Gateshead Millennium Bridge opens downstream.
2010: Other
The kittiwakes that nest on the bridge and neighbouring buildings, some 700 pairs and said to be the furthest inland colony in the world, appear on BBC Springwatch. The Tyne Kittiwake Partnership is formed to protect them, and in 2011 an alternative nesting tower is proposed.
28 June 2012: Disaster
Lightning strikes the arch during a storm that drops a month's rain on Tyneside in two hours. Flash flooding follows across Newcastle.
July 2012: Commemoration
For the London Olympics, rings more than 25 metres wide and 12 metres tall, over four tonnes, are hung from the arch, the largest in the country. During the torch relay, Bear Grylls zip-wires from the arch down to the Gateshead quayside.
29 October 2017: Commemoration
Freedom on the Tyne closes the Freedom City festival, fifty years after Martin Luther King came to Newcastle to receive an honorary degree from the university. The roads around the bridge are shut for the event, and the crowd sees the bridge as Tyneside's echo of the Edmund Pettus Bridge at Selma. The finale ends with a Jarrow Crusade segment.
11 September 2023: Renovation
A four-year restoration begins, after government funding lifts the estimated cost from £12 million to about £32 million. Scaffolding goes up below the deck to allow repainting of rusted steel, structural repairs, new joints, drainage and waterproofing. The aim is to finish by the centenary in 2028.
April 2024: Renovation
Work on the main deck starts, with an overnight full closure on 3 April and lane restrictions after. Esh Construction leads the repairs, which by autumn 2025 include more than 350 repairs and 2,000 replaced rivets, with scaffolding moving on to the parapets and then the arch. Visitors today may find the bridge still wrapped in scaffold, with the work due to end by 2028.