Thames Tunnel
Marc Brunel tried something engineers had judged impossible: a tunnel under the Thames, through soft, waterlogged ground, using a moving iron shield of his own invention. With his son Isambard as a young resident engineer, he drove it from Rotherhithe to Wapping between 1825 and 1843, through six floods, a death toll of at least six, and a seven year shutdown while the money ran out. It is the first tunnel known to have been built successfully under a navigable river. Meant for carriages, it opened as a foot tunnel and drew millions of visitors at a penny each before the novelty faded. In 1869 it became a railway tunnel, and it now carries London Overground trains between Rotherhithe and Wapping. Its Rotherhithe shaft is the home of the Brunel Museum.
Timeline
1805: Other
Cornish mining engineer Robert Vazie starts a tunnel under the Thames from Rotherhithe, and Richard Trevithick takes over the work in 1808. A small pilot drift is pushed about 1,000 feet of the 1,200 needed before the river floods it twice and the attempt is abandoned. Engineers conclude that tunnelling under the Thames cannot be done, which is the verdict Marc Brunel will set out to overturn.
March 1825: Construction
Work begins at Rotherhithe on the entrance shaft. An iron ring 50 feet across is built on the ground with brickwork on top, and then it sinks under its own weight, a few inches a day. By the end of the year the shaft is deep enough for the shield to be assembled and the tunnel to start.
18 May 1827: Disaster
After 549 feet have been dug, the roof above the shield gives way and the Thames pours in. Isambard Brunel goes out over the river in a diving bell to find the hole, and the breach is plugged with clay bags and the water pumped out. It is the first flood, and it will not be the last.
10 November 1827: Performance
To reassure nervous shareholders and advertise the unfinished tunnel, the company holds a banquet inside it, six months after the flood. About fifty guests dine by candlelight while the band of the Coldstream Guards plays "See the Conquering Hero Comes" for the Duke of Wellington, one of the tunnel's backers. It is the first dinner eaten under a river, and George Jones paints it.
8 January 1828: Arrival
Dom Miguel, Regent of Portugal, goes down the shaft as Marc Brunel's guest and toasts Portugal, Britain and King George IV. He sees the shield at work only days before the next flood, and a visit like this is how the Brunels keep the tunnel in the public eye while it struggles for money.
12 January 1828: Disaster
A second, worse flood fills the tunnel and drowns six men, among them the miners Collins and Ball. Isambard Brunel, the young resident engineer, is swept up by the water and rescued after the contractor Beamish breaks down a door to reach him. He is badly hurt, is sent away to recover at Brislington near Bristol, and work stops.
9 August 1828: Other
With the money gone, the company bricks up the tunnel face and abandons the works. The shield stands sealed under the river for years while Marc Brunel looks for new backing. The tunnel that seemed so promising is left as a flooded dead end.
December 1834: Transfer
After years of refusals, Marc Brunel secures a Treasury loan of £247,000 that will let the work restart. His backers include Royal Society friends who have formed a dining group called the Tunnel Club. The shield will be replaced, because the old one has rusted in the ground.
March 1836: Other
A new, heavier shield is assembled at the face, the old one having been dismantled in August 1835, and boring resumes. It takes more than five years to finish the crossing. The tunnel that seemed lost is moving again.
23 August 1837: Disaster
The river breaks in again, the first of several floods after the restart. The engineer Thomas Page has warned of the danger and readies a raft, and work resumes after a few weeks. Further floods follow in November 1837, March 1838 and April 1840, but the tunnel is not abandoned again.
11 June 1840: Construction
Work begins on the Wapping shaft, the tunnel's northern end. Its sides are made slightly wider at the bottom, so that it will not stick as the Rotherhithe shaft did when it sank.
16 November 1841: Construction
The shield breaks through to the Wapping shaft, and Thomas Page presents Marc Brunel with a clod of earth from the far side. The tunnelling is finished after sixteen years, with Marc now in his seventies. Lighting, roadways and staircases still have to be fitted.
2 February 1842: Arrival
Frederick William IV, King of Prussia, goes down the shaft early in the morning and is met by Isambard Brunel. Seeing the gas-lit corridors he says "How beautiful this is!", and he asks how much water lies above his head. The tunnel is almost complete, and royal visitors are already making it famous.
25 March 1843: Commemoration
The Thames Tunnel opens to the public, 1,200 to 1,300 feet long and lit by gas. About 50,000 people pay a penny to walk through in the first 27 hours, and a million in the first ten to fifteen weeks. Souvenir handkerchiefs, snuff boxes and needle cases are on sale. The carriage ramps are never built, because the money is not there, so only pedestrians use the tunnel.
July 1843: Arrival
Queen Victoria and Prince Albert make an impromptu visit by royal barge. A stallholder tears up his silk handkerchiefs for her to walk on, and the locked-in crowd sings the national anthem as she leaves. The Queen is sorry to find that Marc Brunel is not there to receive her.
1844: Other
On the first anniversary the tunnel holds a three day fair, which draws 66,000 visitors, and a fair follows each spring after. The shop alcoves sell souvenirs and refreshments, and musicians play underground. Even so the penny tolls never repay the cost, and the tunnel never pays a dividend.
1855: Other
The American writer Nathaniel Hawthorne walks through and finds a long gas-lit arcade of stalls kept by women who plead with passers-by to buy. He calls the tunnel an "entire failure" for its present use. By now it has the nickname "Hades Hotel" and a reputation for pickpockets and prostitution.
September 1865: Transfer
The East London Railway Company buys the failing tunnel for £800,000. The foot passage is to become a railway, and the company that built it is wound up by Act of Parliament in 1866.
7 December 1869: Other
The first train runs through the tunnel, as part of the East London Railway. The Brunels' walkway is now a railway, and soot from the steam engines still blackens the shaft wall. The Rotherhithe shaft serves as a ventilation shaft.
1884: Conversion
The disused north shaft at Wapping becomes a station on the line, so travellers now step out where Brunel's workmen once broke through.
1940s: Other
In the Second World War a metal roof is put over the Rotherhithe shaft to hide the lights of the trains below from German bombers.
27 April 2010: Other
After closing in December 2007 for the extension of the East London Line, the tunnel reopens to mainline trains as part of London Overground. It is the same bore the Brunels drove under the river, and it carries trains today.
2016: Other
The old Rotherhithe shaft is opened to visitors, with a new staircase, for the first time in over 150 years, as part of the Brunel Museum. People can stand in the smoke-blackened brick chamber where the tunnel began, and look down at the trains running below.