Thames and Medway Canal

A canal about six miles long linking the Thames at Gravesend with the Medway at Frindsbury near Strood, in Kent. It was first proposed to let naval craft pass between the Thames dockyards and Chatham without the long and dangerous voyage round the Isle of Grain, and was engineered by Ralph Dodd, Ralph Walker and William Tierney Clark. Its Higham Tunnel was the second longest canal tunnel in Britain and had the largest bore. The canal opened in 1824 after the wars that justified it had ended, never made money, and in the 1840s the tunnel was handed over to the railway. The Gravesend basin and lock, now Grade II listed, are the only part still navigable. Also known as the Gravesend and Rochester Canal in its early planning.

Timeline

1799: Other

With France at war with Britain, the engineer Ralph Dodd publishes a pamphlet urging a canal from Gravesend to Chatham. Ships carrying ordnance from Deptford and Woolwich would no longer run the gauntlet of French privateers in the Thames estuary, or sail 47 miles round the Isle of Grain. Dodd puts the cost at £24,576 and hopes to pay part of it by selling the dug chalk as agricultural lime.

16 May 1800: Founding

The canal company receives its Act of Parliament and digging begins at the Gravesend end. By now the estimated cost has more than doubled to £57,433. The basin, curved sea walls and unusual barrelled lock chamber on the Thames frontage are built first, between 1799 and 1801.

1801: Other

Four miles of canal are dug as far as Higham, and then the money runs short. The new engineer Ralph Walker warns that the whole canal will cost far more than the revised estimate, and work stops. Dodd has probably left the project by 1804, and the unfinished canal waits many years for a route through the chalk hills beyond.

1819: Construction

Work begins on the tunnel that will carry the canal through the chalk between Higham and Strood, nearly 3,950 yards long. Designed by William Tierney Clark, it is over 26 feet wide and 35 feet high. It becomes the second longest canal tunnel in Britain, though with the largest cross section.

14 October 1824: Founding

The canal opens at last, completed by William Tierney Clark after five Acts of Parliament and a cost of about £260,000. The Napoleonic wars that justified it are long over, so the naval purpose has faded. Its trade is in agricultural produce, beer, cement and groceries.

1830: Renovation

The tunnel is closed for two months while a passing place open to the sky is dug in the middle. It divides the long bore into the Higham and Strood tunnels, so that boats can pass each other.

1846: Transfer

The canal never pays its way, its walls leak and the water drops with every spring tide. In 1844 the company lays a single railway track beside the canal and through the Higham Tunnel, carried on timbers over the water. Within two years the company sells the tunnel to the South Eastern Railway, which fills in the canal from Higham to Frindsbury and lays a double track.

1934: Other

The stretch between Gravesend and Lower Higham, which has stayed navigable, is officially abandoned. Barges had carried cargo along it into the 1930s.

1940s: Destruction

In the Second World War enemy action blows the outer lock gates off the lock chamber at Gravesend, and they are never replaced. London's bomb rubble is also tipped in to fill parts of the canal.

October 2004: Renovation

The Gravesend basin, the only navigable part of the canal, is dredged and its lock gates renovated. The Thames and Medway Canal Association, which took over the canal in 1976, keeps this fragment alive. The railway tunnel is closed that year for relining and reopens on 17 January 2005.