Sizewell B power station
Sizewell B is Britain's only commercial pressurised water reactor, a white-domed station on the Suffolk coast beside the older Sizewell A, and the last nuclear station the country completed for decades. It was announced as a gas-cooled design in 1969, a heavy water design in 1974 and a pressurised water design in 1980, then fought through one of the longest public inquiries Britain has held. Built by John Laing to a Westinghouse design, it cost about £2 billion and has fed the grid since 1995. Owned first by British Energy and since 2009 by EDF, it is now set to run to 2055.
Timeline
1980: Other
After a gas-cooled reactor was announced for Sizewell in 1969 and a steam-generating heavy water design in 1974, the government settles on a pressurised water reactor. It is the first of its kind in Britain, and it is modelled on an American plant at Portland, Oregon. The choice draws strong opposition from local groups and anti-nuclear campaigners.
January 1983: Other
The public inquiry into the pressurised water reactor opens and sits for 340 days over more than two years, taking over 16 million words of evidence, a record at the time. More than 4,000 objectors write in. Around 60 women sing at the back of the hall while the architect Brian Henderson gives evidence, so that he has to nearly shout.
1987: Other
The inquiry chairman, Sir Frank Layfield, reports that, subject to a satisfactory safety case, there are no substantive reasons to stop the project. In August the Nuclear Installations Inspectorate issues the licence to proceed with construction.
18 July 1988: Construction
Construction begins on the shore beside Sizewell A, with John Laing as main contractor. The work includes one of Britain's longest non-stop concrete pours, 5,200 cubic metres over 55 hours for the 4 metre thick base. Over 20,000 jobs are created, many with local firms.
1994: Other
Sizewell B wins the Supreme Award at the British Construction Industry Awards, with the project completed on schedule. Its 65 metre high containment, with 1.4 metre thick walls, is topped by a white dome that the architects, Yorke Rosenberg Mardall, chose after the Central Electricity Generating Board wanted a square box on top.
14 February 1995: Founding
The reactor is synchronised with the National Grid for the first time and begins supplying power. The station has cost about £2 billion at 1987 prices. It is Britain's first and only pressurised water reactor station.
27 May 2008: Other
An unplanned shutdown cuts the station's supply to the grid. Its then owner, British Energy, says the fault lay in conventional equipment, not the nuclear part of the plant.
February 2009: Transfer
British Energy, the owner of the station, is sold to the French state-backed group Électricité de France. Sizewell B passes to EDF Energy, which still operates it, and it is effectively owned by the French government from then on.
17 March 2010: Other
The reactor is taken offline for an extended period after high moisture is found in the containment building, traced to a fault in a pressuriser heater.
2 July 2010: Disaster
A minor fire breaks out just before nine in the evening on the second floor of the charcoal adsorber building. Emergency services attend, the adsorber is flooded, and the fire is under control by half past three the next morning.
2 March 2012: Other
An electrical fault trips the reactor in an unplanned shutdown. It restarts about a week later, at half capacity on a single turbo-alternator, and by June runs under carefully controlled operation.
2013: Construction
A remote Emergency Response Centre is inaugurated, built in line with the recommendations that followed the Fukushima disaster. In the same year the reactor is uprated by one per cent.
January 2014: Construction
Work starts on a dry store for spent fuel, so that used fuel can be kept on site in casks rather than only in cooling ponds. The store is inaugurated in April 2016 and the first cask is installed in March 2017. It is meant to take fuel produced until at least 2035.
2021: Other
An outage stretches past four months after excessive wear is found on stainless steel thermal sleeves in the control rod mechanisms. Output for the year falls to a capacity factor of 63.9 per cent, against 82.9 per cent over the station's life.
8 July 2026: Other
The government and EDF agree terms for a 20-year lifetime extension to 2055, under a Contract for Difference at £70.50 per megawatt hour (2025 prices) from 2035. Designed for 40 years, the reactor is now set to run for about 60, and the extension is expected to support about 900 skilled jobs on site. Centrica, which holds 20 per cent of the station, backs the deal.