Portsmouth Block Mills
At its height in 1808 this modest brick complex in Portsmouth Dockyard turned out 130,000 ships' pulley blocks a year with 45 metal machines, so that ten unskilled men did the work of 110 skilled blockmakers. It was the first place in the world to use all-metal machine tools for mass production, and it was built over an old basin and powered by the Royal Navy's first steam engines. The machinery was patented by Marc Isambard Brunel, built by Henry Maudslay and housed in the wood mills of Samuel Bentham, Inspector General of Naval Works, with Simon Goodrich bringing it into full production. The buildings are also called Brunel's Block Mill, or simply the Wood Mills and Block Mills. Block making ended in the 1960s, and the Grade I listed, scheduled buildings still stand in the working naval base beside the Great Basin, with a few original machines inside.
Timeline
1690s: Construction
Edmund Dummer, building the first great dock system at Portsmouth, digs a second rectangular wet dock north of his Great Basin. Known as the Upper Wet Dock or North Basin, it is finished by about 1698. Its quay walls still lie beneath the site of the later mills.
1770: Conversion
The basin, left without a purpose since the dry dock beside it was rebuilt in 1737, becomes a huge reservoir into which the surrounding dry docks drain by gravity. A masonry platform is built out into it, carrying two horse-gins that drive sixteen chain pumps in a hexagonal well. This pump platform is where steam first arrives.
March 1799: Invention
The Royal Navy's first steam engine starts pumping out the dry docks. Samuel Bentham, Inspector General of Naval Works, had won Admiralty approval in April 1798 for a 12 horsepower table engine designed by James Sadler, the chemist on his staff. It replaces the eastern horse-gin, and Bentham hopes it will also drive saws by day.
1800: Construction
Bentham's plan to fill the reservoir with two tiers of brick vaults is approved, the lower tier still holding the water and the upper meant for storage and building ground. A second, 30 horsepower Boulton and Watt beam engine is ordered as a backup. By April 1802 the vaults are complete, giving him firm ground on which to build a steam-driven wood mill.
14 April 1802: Other
On the day the Admiralty orders two three-storey wood mills built at an estimated £8,827, to a design by the navy's first salaried architect, Samuel Bunce, Bentham writes to the Admiralty's secretary, Evan Nepean, about a model by Marc Brunel for making ships' blocks by machine. Bentham admits he had meant to make blocks here himself, yet calls Brunel's invention well suited to produce blocks of every size with accuracy, uniformity and cheapness. It is a generous verdict that turns his sawmill into a block factory.
2 August 1802: Other
The Admiralty orders the Navy Board to put Brunel's block-making machinery into production with as little delay as possible. The enclosed yard between the two wood mills is built over as a single-storey workshop, held up by turned wooden Tuscan columns found in no other dockyard building. The navy needs over 100,000 blocks a year, about a thousand for each ship of the line, and until now has bought them hand-made from contractors, with uneven quality and uncertain supply. Henry Maudslay is engaged to build the machines.
January 1803: Construction
The first set of Brunel's machines, for medium-sized blocks, is delivered and is working by that summer. In May the Admiralty approves a second set for smaller blocks, which is in use within a year. Brunel works closely with Bentham and Maudslay, and some of their suggestions are built into the machines.
March 1805: Construction
The third and last set of machines, for blocks of 10 to 18 inches, goes into production, completing the plant. Every machine is driven by the two steam engines through shafting that runs up from the vaults and across the ceilings, and a pedimented brick front now dresses the west end of the central range. Bentham himself has been sent to Russia in July, leaving Simon Goodrich and Brunel to bring the mills to full output.
14 September 1805: Other
Lord Nelson visits the Block Mills just before he sails to rejoin the fleet and fight at Trafalgar. His flagship HMS Victory is in the dockyard within sight of the mills, refitting her rigging after two years at sea. It is entirely possible, though unproven, that some of her new blocks come from these machines.
September 1807: Renovation
Brunel and Bentham feel confident enough to declare that the machinery can supply all the needs of the Royal Navy. The old single-acting Sadler engine, which cannot give the woodworking machines a steady enough rotary motion, is replaced by a more powerful double-acting 30 horsepower Murray and Wood table engine, with a new boiler house and chimney.
1808: Other
In its first full working year the mills turn out 130,000 blocks on 45 machines of 22 types. Ten unskilled men now do what 110 skilled blockmakers did, and the system is designed to be worked by labourers, not craft-trained apprentices. This is the peak of the mills as a block factory and a landmark in mass production.
1812: Publication
Rees's Cyclopaedia devotes 18 pages and seven plates to Brunel's machinery, and its fame spreads through the Edinburgh Encyclopaedia and Britannica too. A procession of visitors, foreign ones among them, comes to marvel until 1815. A later encyclopaedia calls the machinery one of the wonders of the world.
1815: Other
The Admiralty has come to rely so heavily on these machines, and so fears a fire in the mills, that Brunel has a duplicate set made. It is stored in a fireproof room at the new Chatham sawmills, and its eventual fate is unknown.
1837: Renovation
The mills keep working into the Victorian era. A new Boulton and Watt engine replaces the original in the west engine house, the east engine having been given a beam engine in 1830. A saw-mill with a grindstone house is added to the north, later demolished.
c. 1908: Conversion
Electricity replaces steam by 1908. Both boiler chimneys are cut down and capped, the old well is sealed, and the engines that powered the first mass production fall silent. The small Georgian mills are now dwarfed by the big workshops and foundries built around them.
1930s: Transfer
As the machines' importance is recognised, the Admiralty gives eight of them to the Science Museum in London between 1933 and 1951. Portsmouth City Museum later receives three more. The Science Museum shows them as the first production line.
1965: Other
The mills close after 160 years, apart from some leatherworking, ending block making here. Hosemakers keep part of the south range until the mid 1980s, and the Ministry of Defence holds a residual use until 1986.
1966: Commemoration
The Block Mills are scheduled as an Ancient Monument. The Ancient Monuments Board soon backs taking them and their contents into State care as a museum of dockyard engineering, but the plan stalls while the Ministry of Defence keeps using part of the building. The mills then stand largely empty, with fabric slowly deteriorating, for some twenty years.
May 2003: Other
English Heritage surveys the building from May to September, as the Royal Navy and heritage bodies weigh its future, and a preservation project follows in 2006. The Grade I listed mills still stand in the naval base, closed to the public, with a lignum vitae saw, a treenail machine and overhead line shafting in place.