London Gateway

Where Shell Haven's oil tanks and chimneys once stood on the north bank of the Thames estuary at Thurrock, Essex, the biggest container cranes in Britain now load and unload ships. The marshy inlet at the mouth of Shell Haven Creek appears on maps as early as 1596, became a Shell refinery from 1916 and closed in 1999 after more than eighty years of refining. DP World bought the 1,500 acre site in 2006 and turned it into a £1.5 billion deep-water port and logistics park, which opened in 2013 and now anchors the Thames Freeport. It has also been known as DP World London Gateway, and the site as Shell Haven or Shellhaven.

Timeline

1916: Founding

Refining begins at Shell Haven on a 40-hectare site, where a distillation plant turns out fuel oil for the Admiralty. Shell has stored petroleum here in iron tanks since a licence of 1912, so the creek shore known from maps since the sixteenth century becomes an oil works in the middle of the First World War. In 1919 the unit is switched to making road-surfacing bitumen.

September 1940: Other

In September 1940, at the height of the Battle of Britain, the refineries and oil tanks at Thames Haven, Shell Haven and Coryton make a sitting target for German bombers. The flat estuary shore gives them nowhere to hide, and the oil works become a prime objective for air raids.

1950: Construction

The postwar expansion comes on stream. Shell's board sanctioned a large new refinery in 1948, built mainly to process Kuwait crude, and in 1950 its first crude distillation unit and three steam boilers are commissioned on 400 hectares west of the original works. More units follow through the 1950s and 1960s, and by 1992 the plant covers 800 hectares and handles 4.6 million tonnes a year.

1970s: Disaster

Three major fires break out at the refinery between 1970 and 1973. They show how dangerous the work is at an installation of this size.

1999: Destruction

Shell closes the refinery, ending more than eighty years of oil refining here. A team picked from the workforce oversees decommissioning and demolition, and everything goes except the bitumen plant and some storage tanks. Some 1,500 acres of brownfield land are left empty on the estuary.

2006: Transfer

DP World, the Dubai ports operator, acquires the empty refinery site as part of its purchase of P&O. It plans a deep-water container port with a logistics park behind it. In May the government gives its approval, and Gordon Brown names the scheme one of four economic hubs of the Thames Gateway.

February 2010: Construction

Building starts at last, after the financial crisis and DP World's own debt troubles delayed the project. The first stage is a £400 million dredging and reclamation job by a joint venture of Laing O'Rourke and Dredging International, which carves new quays out of the estuary.

March 2013: Arrival

The first three of eight quay cranes arrive from the ZPMC yard in Shanghai. Each boom reaches 138 metres and each machine weighs 1,848 tonnes, tall enough to dwarf the London Eye and sized for the biggest container ships afloat.

6 November 2013: Founding

The port opens when the 58,000-tonne MOL Caledon docks, laden with fruit and wine from South Africa. The £1.5 billion terminal, owned by Dubai-based DP World, is built to handle 3.5 million containers a year. Unite has protested here over union recognition and argues the port will draw work from other UK ports, while David Cameron has called it an "emblem of ambition".

10 April 2017: Other

The first rail freight service from the UK to China leaves the port's rail terminal and reaches Yiwu in Zhejiang after 19 days, crossing France, Belgium, Germany, Poland, Belarus, Russia and Kazakhstan. The port is also gaining sea traffic that spring: its third berth opens and the carriers of THE Alliance, Hapag-Lloyd, NYK, K-Line, Mitsui O.S.K. Lines and Yang Ming, announce calls here.

May 2018: Founding

UPS opens a 32,000 square metre sorting hub in the logistics park, able to process about 30,000 packages an hour. It is the second big occupier after Lidl's distribution centre, which began operating in March 2017, and shows the old refinery land filling with warehouses.

15 September 2021: Other

DP World announces a fourth berth, an investment of £300 million, to raise capacity by a third and take ships of 23,000 to 24,000 containers. The decision follows a record year in which the port handles about 1.8 million containers, 15 per cent above the previous best.

19 November 2021: Founding

The Thames Freeport takes effect, with London Gateway at its heart alongside Tilbury and Dagenham. Goods moving through the designated tax sites enjoy customs and tax advantages. The old refinery shore is now part of one of Britain's post-Brexit trade zones, with four berths working and more planned.