Haverhill Waterworks

Haverhill Waterworks is the public water supply works built in Camps Road, one of the highest points in Haverhill, Suffolk, and opened in 1897. It replaced the polluted shallow wells the town had relied on, which had brought repeated typhoid. John Kemp prepared the plans, Surveyor Thomas Cockrill supervised the works, and Crossley Brothers of Manchester supplied the machinery. It used James Atkinson's pneumatic pumping system, described in 1908 as the first installation of that system in the world.

Timeline

1880s to 1890s: Disaster

Haverhill drinks from shallow wells that are badly polluted. Over these years 234 cases of typhoid are recorded in the town, 18 of them fatal, along with 63 cases of continued fever. The toll drives the demand for a proper public supply.

1897: Construction

The new waterworks open on Camps Road, high above the town. A gas engine from Crossley Brothers drives an air compressor that alternately fills and empties two closed vessels, lifting water from a well 253 feet deep to settling tanks and a covered reservoir. It is the first working installation of James Atkinson's pneumatic pumping, built from John Kemp's plans for over £10,000 and supervised by Surveyor Thomas Cockrill.

1890s to 1900s: Other

With clean water now piped through four miles of mains, typhoid in Haverhill falls away. Only 19 cases are notified between 1898 and 1907, three of them fatal, and several years pass with none at all. Alderman W. B. Gurteen's hope that the works would not burden the rates is met with ratepayer complaints about the cost.

c. 1905: Renovation

A new set of pumping machinery is installed at the works, two or three years before 1908. It brings considerable savings in running costs, which eases some of the complaints about expense.