Hainault Depot

Hainault Depot is the Central line train depot on the Hainault loop in north-east London, built under the London Passenger Transport Board's 1935 to 1940 New Works Programme and designed to handle 344 cars. Work began in 1939 but the war left it unfinished and cut off from the railway, and the War Office and the US Army Transportation Corps used it instead. It came into use for Tube stock from December 1947 and has since stabled Standard, 1960, 1962 and 1992 stock.

Timeline

1939: Construction

Work starts on a great new depot for the Central line, part of the London Passenger Transport Board's New Works Programme. Tracks are laid, but the depot is meant to serve an extension that has yet to be completed. It is designed to hold 344 cars.

1939: Occupation

With war declared, building work stops and the half-finished depot sits detached from the railway. The War Office takes it over for its own purposes. For several years it serves the war effort, not the Tube.

1943 to 1945: Occupation

The US Army Transportation Corps moves in and uses the depot to assemble rolling stock. The work continues until 1945. Meanwhile 190 cars of displaced standard stock are also stored there for a time.

14 December 1947: Founding

The depot comes into use for Tube stock as the line from Newbury Park is electrified, so empty trains can reach it. After eight years as a military site it finally does the job it was built for.

31 May 1948: Transfer

Electric trains run from Newbury Park to Hainault, with the depot now fully operational. The depot serves a working passenger line. Electric trains from Woodford reach it too on 21 November 1949, completing the loop.

September 1960: Other

New 1959 and 1960 stock arrives and Hainault has its full complement of 43 eight-car trains. The experimental 1960 stock is also tried here, including automatic train operation, ahead of the Victoria line. Some 1967 Victoria line stock is later stabled here while its ATO equipment is tested on the Woodford to Hainault branch.