Dale Dike Reservoir
On the night of 11 March 1864 the brand new dam here burst, and more than 690 million gallons of water tore down the Loxley and Don valleys into Sheffield in the Great Sheffield Flood, killing at least 240 people. The reservoir, also spelled Dale Dyke and known in 1864 as the Bradfield Reservoir, was built by the Sheffield Waterworks Company from 1859 on the Dale Dike above Low Bradfield, to feed the mills of the Loxley valley and to give Sheffield a limited supply of running water. The disaster brought a government inquiry, an inquest, a Board of Inundation Commissioners and thousands of compensation claims. A smaller dam was built upstream in 1875, and the reservoir still serves Sheffield's water supply today.
Timeline
1859: Construction
The Sheffield Waterworks Company begins an earth dam across the Dale Dike in Bradfield Dale. Sheffield has grown from 45,748 people in 1801 to 185,157 in 1861 and needs clean water, while the mills of the Loxley valley need a steady flow. John Towlerton Leather designs the dam and John Gunson is resident engineer, directing the work on site.
1863: Construction
The embankment is finished, about 95 feet high and 500 feet wide, with a puddle clay core meant to hold the water. It is passed as satisfactory and the reservoir is allowed to begin filling. By the second week of March 1864 the water stands within 2 feet 4 inches of the crest, in a strong south-westerly gale.
1864: Other
The coroner's jury declares that the reservoir was defective from the start and that the Waterworks Company had shown gross and culpable negligence. It regrets that it cannot return a verdict of manslaughter, and it urges the Government to inspect reservoirs. A Home Office inquiry led by Robert Rawlinson and Nathaniel Beardmore also looks into the failure, while the engineers hired by the company and by the Corporation reach opposite conclusions.
March 1864: Other
In the days after the flood the Loxley valley becomes a sightseeing destination. Extra trains bring crowds to see the ruins, and people sell hot chestnuts by the roadside, so that the valley is said to look like a fairground. The Sheffield Photo Company advertises an album of flood scenes within the week.
11 March 1864: Other
At about half past five in the evening the quarryman William Horsefield spots a crack in the embankment, no wider than a penknife blade, and warns the workmen nearby. By seven it is as wide as a man's finger and a rider is sent galloping to Sheffield for the engineer John Gunson. Gunson arrives after ten and tries to ease the pressure by blowing up the waste weir, but it is too late.
11 March 1864: Disaster
Near midnight the dam bursts and the reservoir empties in under an hour, sending more than 690 million gallons down the valley at up to 18 miles an hour. Bradfield, Damflask, Little Matlock and Loxley lie in its path, and about 43 mills are wrecked. The inquiry points to a fault in the ground beneath the embankment and poor quality control over the clay core, though the exact cause is never settled.
12 March 1864: Disaster
Where the valley narrows at Malin Bridge, the water has nowhere to spread, and the village is hit hardest. 102 people die here, 11 of them from one family, and the Cleakum Inn is smashed to pieces. Below, the flood passes through Hillsborough, Owlerton and the Wicker into the centre of Sheffield and on to Attercliffe and Rotherham, with 15 bridges swept away. The youngest victim is two days old, the eldest 78.
14 March 1864: Other
At a meeting called by the Mayor, Thomas Jessop, Sheffield sets up a relief fund for the people hit by the flood, and over £4,000 is pledged on the spot. Working men are asked to give a day's wage, and Queen Victoria sends a personal cheque for £200. The fund passes £42,000 in subscriptions.
4 October 1864: Other
Three Inundation Commissioners take their seats in Sheffield Town Hall to judge claims against the Waterworks Company. They face about 7,500 claims for loss of life and property, worth more than £455,000. All but 650 are settled without arbitration, and those 650 take almost six months.
1875: Construction
A new, smaller dam is built a little way upstream of the burst one, and the reservoir is rebuilt for domestic water supply only. It holds about 72.9 million cubic feet, well below the original.
11 March 2014: Commemoration
On the 150th anniversary, Bradfield and Sheffield remember the flood with talks, an exhibition at Low Bradfield village hall and a memorial service. A stone marks the line of the breached wall, and a plaque in St Nicholas Church, Bradfield, records the disaster. Walkers can follow footpaths around the reservoir, which still supplies Sheffield.