Aldeburgh branch line
A railway from Saxmundham on the East Suffolk Line through Leiston to Aldeburgh, promoted by Samuel Morton Peto and backed by Richard Garrett of Leiston's engineering works. It opened in 1859 and 1860, was taken over by the Great Eastern Railway, and lost its passenger trains in 1966. The section to Sizewell survives as a freight spur serving the nuclear power stations. Also called the Leiston and Aldeburgh branch.
Timeline
1 June 1859: Founding
The line from Saxmundham opens as far as Leiston. It is the work of Samuel Morton Peto and has the support of Richard Garrett, whose engineering works in the town now gain a rail link. A branch into Garrett's works opens the same day.
12 April 1860: Construction
The line is extended about four miles from Leiston to Aldeburgh, giving the seaside town its station. Five trains a day each way run to Saxmundham, and the terminus gets a single platform under an overall roof, unusual for the Great Eastern.
1862: Transfer
The Great Eastern Railway takes the branch over from the Eastern Counties Railway, which had worked it from the start. It stays a Great Eastern line until the grouping of 1923.
1914: Construction
Thorpeness station opens to serve the new holiday village, with a single platform and three old carriage bodies as its buildings. The same year fish traffic ends, as shingle blocks Aldeburgh harbour.
1929: Arrival
The locomotive Sirapite begins work on Garrett's branch at Leiston, replacing the horses, gravity and cable that had moved wagons until then. It keeps working until 1962.
November 1959: Other
Goods traffic is withdrawn from Thorpeness and Aldeburgh, leaving the southern end of the line with passengers only. Closure of the whole branch follows within a few years.
12 September 1966: Other
Passenger services are withdrawn, despite strong local opposition after the Beeching Report of 1963. The last train, a pair of Metro-Cammell diesel units driven by Driver Skeels of Ipswich, is filmed. Track south of Sizewell is later lifted.
1975: Destruction
The Aldeburgh station building is demolished and houses are built on the site. The overall roof had already come down in August 1965.
1980s: Construction
Construction trains use the surviving Sizewell spur to carry materials for Sizewell B power station, as they had for Sizewell A in the 1960s. The line has since carried nuclear flask trains.
2025: Other
The first Sizewell C construction trains run over the branch, after the government confirmed the project in 2022 and the line was upgraded with new signalling, track and crossings.